2020 FALL AMENDMENT CYCLE

The Department of Planning is accepting applications for the Fall Amendment Cycle.  The deadline to submit an application for the Fall Cycle is October 1, 2020.

Tentative Timeline (subject to change):

Planning Commission(s) certification of consistency – November/December 2020

Brief Board of County Commissioners, Public Hearing, Discussion/Decision – December 2020/January 2021

Send to Maryland Department of the Environment for final approval – January 2021

Applications for an amendment to the Carroll County Master Plan for Water and Sewerage must provide complete information and be signed by the applicant requesting the amendment and by the owner of the affected property. Questions pertaining to the information required on the application may be directed to the Carroll County Department of Planning.

Water and Sewerage Master Plan Amendment Procedure 
Water and Sewerage Master Plan Amendment Application